420MW Combined Cycle Gas Turbine Power Plant in Thisvi, Central Greece

The ultramodern plant facility is located on 100 acres of private land in the industrial zone of Thisvi, which operates under a context of clearly defined boundaries and land uses, approved street plan and infrastructure, thus ensuring both the minimization of any environmental impact and further industrial development.

The design and construction of the power plant lasted almost 3 years and absorbed an investment of 275 million euros, including the connection to the high grid and the gas network. During the construction of the Plant, there were more than 250 people, on average, working on the site on a monthly basis, while during the peak of the construction period, the corresponding number exceeded 700 people. Overall, only within the site, more than 1.650.000 employee hours had been dedicated.